• Project : Gor*** Gek**
• Order Type : Type B (There is a prototype.)
• Host : Vict**** L
• Progress : Completing the project
- We confirmed the payment the booking(Sample and Prototype).
- The sample work was completed.
- We got feed back from host.
- We found new fabrics.
- The work of the prototype was completed on March 2, 2020.
- We sent the prototype to the host.
- Shipping date : March 4, 2020
- Completion date of the delivery : March 9, 2020
- We waited for host to order the run.
- Deadline for payment(run) : August 9, 2020
- We confirmed the payment for the run on June 6, 2020.
- Schedule of the run work : August, 2020(This is schedule on the quote.)
- We made the run.
- The work of the run was completed on August 19, 2020.
- We checked the outfits and packaged them.
- Inspection and packaging task were completed on September 10, 2020.
- We sent the goods to the host.
- Shipping date : September 11, 2020
- Completion date of the delivery : September 24, 2020
- The project is completed.