• Project : Theo****
• Order Type : Type B (There is a prototype.)
• Host : Ges** Stu***
• Progress : Completing the project
- The work of the prototype was completed.
- We sent the prototype to the host.
- Shipping date : May 2, 2019
- Completion date of the delivery : May 3, 2019
- We confirmed the payment for the run.
- Schedule of the run work : January, 2020(This is schedule on the quote.)
- The work of the run was completed on March 2, 2020.
- Inspection and packaging task were completed on March 12, 2020.
- We sent the goods to the host.
- Shipping date : March 13, 2020
- Completion date of the delivery : March 16, 2020
- The project is completed.