• Project : Fra** Shee***
• Order Type : Type B (There is a prototype.)
• Host : Ya** Q
• Progress : Completing the project
- We confirmed the payment the booking(Sample and Prototype).
- Schedule of the sample work : November, 2020(This is schedule on the quote.)
This is a schedule for the work start time.
The schedule is subject to change.
- We prepared the materials(fabrics).
- We made the first sample.
- We made the second sample.
- We got feed back from host.
- We made the prototype to reflect modifications of host.
- The prototype work was completed on July 12, 2022.
- We sent the prototype to the host.
- Shipping date : July 15, 2022
- Completion date of the delivery : July 21, 2022
- We waited for host to order the run.
- Deadline for payment(run) : December 21, 2022
- We confirmed the payment for the run.
- Schedule of the run work : October, 2022
This is a schedule for the work start time.
The schedule is subject to change.
- We made the run.
- The work of the run was completed on January 5, 2023.
- We checked the outfits and packaged them.
- Inspection and packaging task were completed on January 12, 2023.
- We sent the outfits in batches by host demand.
- First shipping date : January 13, 2023
- Completion date of the first delivery : January 20, 2023
- Second(last) shipping date : January 17, 2023
- Completion date of the second(last) delivery : January 20, 2023
- The project is completed.