• Project : Ra** A* Gh**
• Order Type : Type B (There is a prototype.)
• Host : Rich*** M
• Progress : Completing the project
- We confirmed the payment the booking(Sample and Prototype).
- Schedule of the sample work : July, 2020
This is a schedule for the work start time.
The schedule is subject to change.
- We prepared the materials(fabrics).
- We made the sample.
- The sample work was completed.
- We got feed back from host.
- We made the prototype.
- The prototype work was completed on December 21, 2020.
- We sent the prototype to the host.
- Shipping date : January 18, 2021
- Completion date of the delivery : February 18, 2021
- We waited for host to order the run.
- Deadline for payment(run) : July 18, 2021
- We confirmed the payment for the run.
- Schedule of the run work : September, 2021
This is a schedule for the work start time.
The schedule is subject to change.
- We made the run.
- The work of the run was completed on December 30, 2021.
- We checked the outfits and packaged them.
- Inspection and packaging task were completed on January 25, 2022.
- The goods was ready for shipment.
- We waited for host's contact.
- We received the shipping information from the host on June 21, 2022.
- We sent the outfits in batches by host demand.
- First shipping date : June 23, 2022
- Second shipping date : June 27, 2022
- Third shipping date : July 5, 2022
- Fourth shipping date : July 12, 2022
- Fifth shipping date : July 15, 2022
- Sixth shipping date : July 21, 2022
- Seventh shipping date : July 26, 2022
- Last shipping date : September 21, 2022
- The project is completed.