• Project : Jul** Winnf****
• Order Type : Type A (There is not a prototype.)
• Host : Wa* L
• Progress : Completing the project
- We confirmed the payment the booking(Sample).
- Schedule of the sample work : November, 2019(This is schedule on the quote.)
- We prepared the materials(fabrics).
- We waited for host to send parts.
- We got the parts on January 29, 2020.
- We rescheduled this project because we got the parts late.
- New schedule of the sample work : February, 2020
- We made the sample.
- The sample work was completed on February 28, 2020.
- We got feed back from host.
- We waited for host to order the run.
- Deadline for payment(run) : July 28, 2020
- We confirmed the payment for the run on July 13, 2020.
- Schedule of the run work : October, 2020(This is schedule on the quote.)
- We made the run.
- The work of the run was completed on November 27, 2020.
- We checked the outfits and packaged them.
- Inspection and packaging task were completed on January 6, 2021.
- We sent the outfits in batches by host demand.
- First shipping date : January 11, 2021
- Completion date of the first delivery : January 12, 2021
- Second shipping date : January 12, 2021
- Completion date of the second delivery : January 15, 2021
- Third shipping date : January 15, 2021
- Completion date of the third delivery : January 20, 2021
- Fourth shipping date : January 22, 2021
- Completion date of the fourth delivery : February 1, 2021
- The project is completed.