• Project : Jok** (Art*** Fle**)
• Order Type : Type B (There is a prototype.)
• Host : Yut*** H
• Progress : Completing the project
- We confirmed the payment the booking(Sample and Prototype).
- Schedule of the sample work : August, 2021(This is schedule on the quote.)
This is a schedule for the work start time.
The schedule is subject to change.
- We prepared the materials(fabrics).
- We made the first sample.
- We made the second sample.
- We got feed back from host.
- We made the prototype to reflect modifications of host.
- The prototype work was completed on May 10, 2022.
- We sent the prototype to the host.
- Shipping date : June 9, 2022
- Completion date of the delivery : June 20, 2022
- We confirmed the payment for the run.
- Schedule of the run work : July, 2022
This is a schedule for the work start time.
The schedule is subject to change.
- We waited for host feedback.
- We made the run.
- The work of the run was completed on February 21, 2023.
- We checked the outfits and packaged them.
- Inspection and packaging task were completed on March 8, 2023.
- We sent the outfits in batches by host demand.
- First shipping date : March 9, 2023
- Completion date of the first delivery : March 14, 2023
- Second(last) shipping date : March 17, 2023
- Completion date of the second(last) delivery : March 24, 2023
- The project is completed.