• Project : Do* Vi** Corl****

• Order Type : 3rd run

• Host : Mi** F

• Progress : Completing the project

 - We confirmed the payment for the run.

 - Schedule of the run work : April, 2020(This is schedule on the quote.)

 - The work of the run was completed on May 11, 2020.

 - Inspection and packaging task were completed on June 19, 2020.

 - We sent the outfits in batches due to large quantities.

 - First shipping date : June 22, 2020

 - Completion date of the first delivery : July 14, 2020

 - Second shipping date : June 24, 2020

 - Completion date of the second delivery : July 8, 2020

 - Third shipping date : July 17, 2020

 - Completion date of the third delivery : August 4, 2020

 - Last shipping date : July 29, 2020

 - Completion date of the last delivery : August 8, 2020

 - The project is completed.


첨부파일
비밀번호 수정 및 삭제하려면 비밀번호를 입력하세요.
댓글 수정

비밀번호 :

/ byte

비밀번호 : 확인 취소

댓글 입력
댓글달기 이름 : 비밀번호 : 관리자답변보기

영문 대소문자/숫자/특수문자 중 2가지 이상 조합, 10자~16자

/ byte

왼쪽의 문자를 공백없이 입력하세요.(대소문자구분)

관리자에게만 댓글 작성 권한이 있습니다.

© Copyright TORIBOX. All Rights Reserved.