• Project : To** Sta**
• Order Type : Type B (There is a prototype.)
• Host : Yut*** H
• Progress : Completing the project
- We confirmed the payment the booking(Sample and Prototype).
- Schedule of the sample work : June, 2020(This is schedule on the quote.)
- We prepared the materials(fabrics).
- We made the sample.
- The sample work was completed on August 17, 2020.
- We got feed back from host.
- We made the prototype.
- The prototype work was completed on January 16, 2021.
- We sent the prototype to the host.
- Shipping date : January 22, 2021
- Completion date of the delivery : February 1, 2021
- We waited for host to order the run.
- Deadline for payment(run) : July 1, 2021
- We confirmed the payment for the run.
- Schedule of the run work : July, 2021(This is schedule on the quote.)
- We made the run.
- The work of the run was completed on August 5, 2021.
- Inspection and packaging task were completed on August 18, 2021.
- We sent the outfits in batches by host demand.
- First shipping date : August 26, 2021
- Completion date of the first delivery : September 3, 2021
- Second shipping date : August 30, 2021
- Completion date of the second delivery : August 31, 2021
- Third shipping date : September 6, 2021
- Completion date of the third delivery : September 12, 2021
- Last shipping date : September 13, 2021
- Completion date of the last delivery : September 22, 2021
- The project is completed.