• Project : Eth** Hu**
• Order Type : Type B (There is a prototype.)
• Host : Ding*** P
• Progress : Completing the project
- We confirmed the payment the booking(Sample and Prototype).
- Schedule of the sample work : May, 2020(This is schedule on the quote.)
- We prepared the materials(fabrics).
- We made a sample on February 11, 2021.
- We got feed back from host.
- We made the prototype to reflect modifications of host.
- The prototype work was completed on March 19, 2021.
- We sent the prototype to the host.
- Shipping date : March 22, 2021
- Completion date of the delivery : March 26, 2021
- We waited for host to order the run.
- Deadline for payment(run) : August 26, 2021
- We confirmed the payment for the run.
- Schedule of the run work : June, 2021(This is schedule on the quote.)
- We made the run.
- The work of the run was completed on September 3, 2021.
- We checked the outfits and packaged them.
- Inspection and packaging task were completed on September 13, 2021.
- We waited for host's contact.
- We sent the outfits in batches by host demand.
- First shipping date : October 8, 2021
- Completion date of the first delivery : October 24, 2021
- Last shipping date : October 19, 2021
- Completion date of the last delivery : October 25, 2021
- The project is completed.