• Project : Ne*
• Order Type : Type B (There is a prototype.)
• Host : Zha** X
• Progress : Completing the project
- We confirmed the payment the booking(Sample and Prototype).
- Schedule of the sample work : September, 2019(This is schedule on the quote.)
- We prepared the materials(fabrics).
- We made the sample.
- The sample work was completed on August 20, 2020.
- We got feed back from host.
- We made the prototype to reflect modifications of host.
- The prototype work was completed on September 15, 2020.
- We sent the prototype to the host.
- Shipping date : September 17, 2020
- Completion date of the delivery : September 22, 2020
- We waited for host to order the run.
- Deadline for payment(run) : February 22, 2021
- We confirmed the payment for the run.
- Schedule of the run work : April, 2021(This is schedule on the quote.)
- We made the run.
- The work of the run was completed on June 4, 2021.
- Inspection and packaging task were completed.
- We sent the outfits in batches by host demand.
- First shipping date : July 26, 2021
- Completion date of the first delivery : August 6, 2021
- We waited for host's contact.
- Last shipping date : October 1, 2021
- Completion date of the last delivery : October 13, 2021
- The project is completed.