• Project : Dr. Al** Gra**
• Order Type : Type A (There is not a prototype.)
• Host : Jam** L
• Progress : Completing the project
- We confirmed the payment the booking(Sample).
- Schedule of the sample work : April, 2019(This is schedule on the quote.)
- We are preparing materials(fabrics).
- We have not received a body and a material from a host yet.
- We waited for host to send the body and the materials.
- We got the parts on January 22, 2020.
- We rescheduled this project after the sample work of other projects was completed.
- We made the sample.
- The sample work was completed on August 21, 2020.
- We waited for host to order the run.
- Deadline for payment(run) : January 21, 2021
- We confirmed the payment for the run on April 2, 2021.
- Schedule of the run work : May, 2021(This is schedule on the quote.)
- We made the run.
- We waited for host to send the parts.
- The work of the run was completed on November 3, 2021.
- We checked the outfits and packaged them.
- Inspection and packaging task were completed on November 6, 2021.
- We sent the goods to the host.
- Shipping date : November 15, 2021
- Completion date of the delivery : November 29, 2021
- The project is completed.