• Project : Sebas****
• Order Type : Type B (There is a prototype.)
• Host : Zha** X
• Progress : Completing the project
- We confirmed the payment the booking(Sample and Prototype).
- We prepared the materials(fabrics).
- We made the sample.
- The sample work was completed on September 30, 2019.
- We got feed back from host.
- We made the new sample to reflect modifications of host on October 15, 2019.
- We got feed back from host.
- We made the prototype to reflect modifications of host.
- The prototype work was completed on December 20, 2019.
- We sent the prototype to the host.
- Shipping date : December 27, 2019
- Completion date of the delivery : December 31, 2019
- Deadline for payment(run) : May 31, 2020
- We confirmed the payment for the run on April 17, 2020.
- Schedule of the run work : June, 2020(This is schedule on the quote.)
- We made the run.
- The work of the run was completed on June 26, 2020.
- We checked the outfits and packaged them.
- Inspection and packaging task is completed on July 7, 2020.
- We sent the goods to the host.
- Shipping date : July 8, 2020
- Completion date of the delivery : July 13, 2020
- The project is completed.